Preparation of a civil design including concept and construction plans for council and civil contractor. The Development included an extensive amount of earthworks as 50,000 cubic metres of earth was moved onsite. Water Quality Measures included the design of a 1,800 square metre wetland.
CLIENT
Mirvac
PROJECT TASKS
- Professional services provided include:
- Concept and construction plans for both storm water, road, and carpark design
- Implementation of Water Sensitive Urban Design measures.
ENGINEERING DISCIPLINE RESPONSIBILITIES
- Preparation of the bulk earthworks volumes and level coordination for the entire site
- Concept and construction designs for all the civil infrastructure across the subdivision including drainage, roads and Water Sensitive Design measures
- Concept and construction design for Water quality Design measures
- Co-ordination with project team including Planners, Landscape Architects, Engineers and Geotechnical Engineers.